Frequently asked questions
LiDAR, met masts, campaign design and bankability explained by our measurement engineers.

LiDAR vs met mast, standalone and hybrid campaigns
A met mast measures wind with cup anemometers and vanes fixed on booms at set heights on a tower. A ground-based wind LiDAR is a laser remote-sensing device that measures wind speed and direction at up to 20 heights between about 40 m and 300 m, without any tower. Both are covered by IEC standards: IEC 61400-50-1 for masts and IEC 61400-50-2 for ground-based LiDAR.
A well-run mast campaign typically reaches 1.5–2.0% measurement uncertainty on wind speed; a verified LiDAR reaches 1.5–4.0%, depending on terrain and verification. When verified against an on-site mast, verification uncertainty falls to about 0.2–0.3%. In complex terrain the LiDAR needs a flow correction (e.g. CFD).
It measures directly at hub height and across the full rotor up to 300 m, deploys in days typically without a construction permit, avoids work at height, can be relocated across the site, and costs less upfront than a hub-height mast.
Where lenders or turbine suppliers need point turbulence intensity from cup anemometers, in complex terrain where MEASNET requires at least one mast, and on long-timeline projects where a permanent reference is valuable. Masts also keep recording in fog, heavy rain or very clean air.
One or more LiDARs as the only on-site wind measurement. It is accepted as bankable in flat and simple terrain under FGW TR6 and MEASNET, provided the LiDAR is verified by an accredited body before and after the campaign.
Yes, with the right approach. We screen every candidate position for terrain complexity, and for bankable results in complex terrain combine LiDARs with at least one reference mast.
A met mast paired with one or more LiDARs on the same site. The mast is the long-term reference and verifies the LiDARs; the LiDARs measure the full rotor height and can roam between turbine clusters. Data availability is typically above 95% with the lowest overall uncertainty.
Campaign duration and when to start
At least 12 complete, consecutive months; 24 months or more is preferred for a lender-grade energy yield assessment. Twelve months captures one full seasonal cycle and is the minimum under MEASNET and FGW TR6.
Yes. P99 provides interim assessments, typically after 3 and 6 months, correlated against long-term reference data. They support early layout and turbine decisions but do not replace the 12-month minimum for a bankable assessment.
As early as possible, ideally once a site has passed desktop screening and land access is secured. Lenders will not close without at least 12 months of site data. Starting with a LiDAR avoids waiting months for a mast permit.
MEASNET requires at least 90% availability of filtered data from the primary sensor (with its backup) over 12 consecutive months, and at least 95% after gap-filling.
Bankability
Data an independent technical adviser and a lender accept as the basis for financing a project: collected with calibrated, traceable instruments, following IEC and national guidelines, with documented installation, monitoring and quality control.
Yes. In simple terrain as a standalone measurement under FGW TR6 and MEASNET, and in complex terrain when combined with flow correction and at least one reference mast. The LiDAR must be classified by an accredited laboratory and verified before and after the campaign.
P50 is the annual energy expected to be exceeded with 50% probability; P90 with 90%. Lenders size debt on P90, so lower uncertainty directly means more debt and better economics. A well-run campaign on a good site gives total uncertainty of about 5–10%.
IEC 61400-50-1 (masts), IEC 61400-50-2 (ground-based remote sensing), IEC 61400-12-1, IEC 61400-15-1:2025 (energy yield and uncertainty), MEASNET site-specific wind conditions v3 (2022), FGW TR6 Rev. 12 and IEA Wind Recommended Practice 15.
Other frequently asked questions
With an autonomous hybrid power supply. P99’s containerised unit combines 940 Wp of solar PV, 8.48 kWh of usable battery storage and an EFOY PRO 2800 methanol fuel cell that starts automatically when solar input is low. The batteries alone run a LiDAR for about 130 hours.
Our LiDAR stations can include a lockable container or trailer, CCTV, GPS tracking and motion detection, all monitored remotely.
Data is transmitted daily and checked by P99 analysts for availability, sensor faults and plausibility. The power system is monitored in real time, so faults are caught before they cause data loss.
A side-by-side test of the LiDAR against a calibrated reference mast at an accredited test site, before and ideally after the campaign. IEC 61400-50-2 and FGW TR6 require it for bankable use.
Yes. P99 designs and installs solar measurement stations and provides solar irradiation analysis and energy yield assessments for PV and hybrid projects.
Based in Sofia, Bulgaria, we run campaigns across Southeast Europe, including Bulgaria, Romania, Serbia, North Macedonia, Albania and Bosnia and Herzegovina, with projects on five continents.
All three. We are an authorised representative of Vaisala WindCube and ZX Lidars, run turnkey campaigns, and provide energy yield assessments from the data.
Accuracy matters. Let’s measure your site.
Tell us about your wind, solar or hybrid project and we will propose a measurement campaign that fits your risk profile and timeline.
Start a conversation →